Title
Change Order No. 2 to Contract 9-13 for Unit W-13 Sewer & Water Reconstruction No. 1 with Kruczek Construction Inc. to increase for additional quantities of 6" storm lateral in the amount of $5,200.00 resulting in a decrease to contingency from $25,200.00 to $20,000.00. No change to overall contract amount.