Title:
|
Request to approve Contract Amendment #1 to Donohue as part of the AWWTP Anaerobic Digester Inspection, Maintenance, and Improvements Project to support Phase 5 Construction Services in the amount of $209,479 increasing the contract amount from $293,755 to $503,234 along with the following 2025-2026 Budget carryover appropriations (2/3 vote of Council required):
Wastewater Utility Fund
2025 Digester Cathodic Protection & Corrosion Control - $316,200
2025 Equipment Repairs & Maintenance - $187,034
2026 Digester Cathodic Protection & Corrosion Control + $316,200
2026 Equipment Repairs & Maintenance + $187,034
|