Title: Contract 21-23 was awarded to SDS Painting Company for $86,330 with a contingency of $10,000 for WWTP V Building Painting Project Phase 2. Change orders were approved totaling $5,810. Final contract amount is $92,140 with a contingency of $4,190. Payments issued to date total $84,588. Request final payment of $7,552.

Title

Contract 21-23 was awarded to SDS Painting Company for $86,330 with a contingency of $10,000 for WWTP V Building Painting Project Phase 2. Change orders were approved totaling $5,810. Final contract amount is $92,140 with a contingency of $4,190.  Payments issued to date total $84,588. Request final payment of $7,552.