File #: 22-0713    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 5/19/2022 In control: Finance Committee
On agenda: 5/23/2022 Final action: 6/1/2022
Title: Request to approve Contract Amendment/Change Order No. 3 to contract 133-21, Unit U-21 Apple Creek Ct & Plamann Park S&W Construction for additional quantities of tree removal and gravel backfill to facilitate sewer construction in the amount of $64,293 resulting in no change to contract contingency. Overall contract increases from $3,999,181 to $4,063,474
Attachments: 1. Unit U-21 Change Order No. 3.pdf

Title

Request to approve Contract Amendment/Change Order No. 3 to contract 133-21, Unit U-21 Apple Creek Ct & Plamann Park S&W Construction for additional quantities of tree removal and gravel backfill to facilitate sewer construction in the amount of $64,293 resulting in no change to contract contingency. Overall contract increases from $3,999,181 to $4,063,474