Title: Contract 28-24 was awarded to Joski Sewer Services for $611,302 for Lead/Galvanized Water Service Replacement. Change orders were approved reducing the contract amount totaling $88,730.29. Final contract amount is $522,571.71. Payments issued to date total $425,129.19. Request final payment of $97,442.52.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Contract 28-24 was awarded to Joski Sewer Services for $611,302 for Lead/Galvanized Water Service Replacement. Change orders were approved reducing the contract amount totaling $88,730.29. Final contract amount is $522,571.71. Payments issued to date total $425,129.19. Request final payment of $97,442.52.