File #: 13-631    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 5/30/2013 In control: Board of Public Works
On agenda: 6/5/2013 Final action: 6/5/2013
Title: Approve Change Order #1 to Contract 9-13 (Unit W-13) Sewer & Water Reconstruction No. 1 with Kruczek Construction, to increase for additional quantity of 12" storm sewer per City request in the amount of $4,800.00, resulting in a decrease to contingency from $30,000.00 to $25,200.00. No change to overall contract amount.
Attachments: 1. BPW Attachment Unit W-13 - 06-05-13 Meeting.pdf
Title
Approve Change Order #1 to Contract 9-13 (Unit W-13) Sewer & Water Reconstruction No. 1 with Kruczek Construction, to increase for additional quantity of 12" storm sewer per City request in the amount of $4,800.00, resulting in a decrease to contingency from $30,000.00 to $25,200.00.  No change to overall contract amount.