Title
Approve Change Order #1 to Contract 9-13 (Unit W-13) Sewer & Water Reconstruction No. 1 with Kruczek Construction, to increase for additional quantity of 12" storm sewer per City request in the amount of $4,800.00, resulting in a decrease to contingency from $30,000.00 to $25,200.00. No change to overall contract amount.