Title
Approve Contract Amendment/Change Order No. 1 to Contract 1-13B for AEHS Stormwater Storage Project Unit T-11 - Waterproofing Sytem with Midwest Industrial Coatings to Increase for Added Product Application On-site Resulting in Higher Bonds/Wages in the Amount of $165,000 and an Increase to Contingency from $25,111 to $100,111. Overall Contract Amount Increases from $1,022,492 to $1,262,492.