File #: 13-1119    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 8/8/2013 In control: Municipal Services Committee
On agenda: 10/8/2013 Final action: 10/16/2013
Title: R/B - Smith - Glendale Avenue from Ballard Road to Roemer Road be reconstructed with concrete pavement and curb and gutter to a width of 48' from back of curb to back of curb, which is 1' narrower than the existing street width. The newly reconstructed Glendale Avenue would include an 8' parking lane along the north side of the street, a 3' buffer area between the parking lane and bike lane, a 5' wide bike lane along the north side of the street, two 12.5' travel lanes, and a 6' wide bike lane along the south side of the street. Parking would be removed from the south side of Glendale Avenue within the proposed project limits. New Sidewalks would be constructed to the right-of-way line along both sides of Glendale Avenue within the project limits. Approved by a vote of Aye-2/Dannecker, Oswald; Nay-1/Martin. Amendment #1 at 9/4/13 Council: Strike "north" in all cases, replace with "south", and vice versa. This amendment will move the proposed parking lane from the north to the s...
Attachments: 1. Glendale Ave drawings.pdf
Title
R/B - Smith - Glendale Avenue from Ballard Road to Roemer Road be reconstructed with concrete pavement and curb and gutter to a width of 48' from back of curb to back of curb, which is 1' narrower than the existing street width.  The newly reconstructed Glendale Avenue would include an 8' parking lane along the north side of the street, a 3' buffer area between the parking lane and bike lane, a 5' wide bike lane along the north side of the street, two 12.5' travel lanes, and a 6' wide bike lane along the south side of the street.  Parking would be removed from the south side of Glendale Avenue within the proposed project limits.  New Sidewalks would be constructed to the right-of-way line along both sides of Glendale Avenue within the project limits.  Approved by a vote of Aye-2/Dannecker, Oswald; Nay-1/Martin.
Amendment #1 at 9/4/13 Council:  Strike "north" in all cases, replace with "south", and vice versa.  This amendment will move the proposed parking lane from the north to the south side of the street.  Approved by a vote of Aye-10; Nay-5.
Amendment #2 at 9/4/13 Council:  In the last sentence, strike "both sides" and replace with "the north side".  This removes the proposed sidewalk from the south side of the road.  Approved by a vote of Aye-8; Nay-7.