File #: 14-1969    Version: 1 Name:
Type: Presentation Status: Filed
File created: 11/13/2014 In control: Finance Committee
On agenda: 12/10/2014 Final action: 12/10/2014
Title: Contract 7-14 was awarded to Nieman Central Wisconsin Roofing for "WWTP CIP Roof Replacement" in the amount of $79,560 with a contingency of $8,000. One change order was issued for a credit of $200. Final contract amount is $79,360 with remaining contingency of $8,000. Payments issued to date total $71,604. Request to issue the final contract payment of $7,756.
Attachments: 1. 2014 WWTP CIP Roof Rplc Final Pymt.pdf
Title
Contract 7-14 was awarded to Nieman Central Wisconsin Roofing for "WWTP CIP Roof Replacement" in the amount of $79,560 with a contingency of $8,000.  One change order was issued for a credit of $200.  Final contract amount is $79,360 with remaining contingency of $8,000.  Payments issued to date total $71,604.  Request to issue the final contract payment of $7,756.