Title:
|
A donation of $500,000 was given to the City of Appleton for the construction of a new eight-court Pickleball Complex at Telulah Park. Construction Contract 21-22 was issued to Northeast Asphalt in the amount of $484,862 for the Pickleball Complex construction. A change order of $101,690 was added to cover lighting, shade structures and furniture. Poor subsoils were discovered during excavation which required $27,592.96 in excavation and additional base, for a contract total of $614,144.96. The new courts are complete. Payments to date total $569,187.71 Request to issue the final payment of $44,957.25.
|