File #: 19-1398    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 9/13/2019 In control: Finance Committee
On agenda: 9/18/2019 Final action: 9/18/2019
Title: Contract Amendment and Change Order No. 1 to contract 81-19 for Unit O-19 CIPP Liner for slip lining of deteriorated 36" Storm Sewer in lieu of originally bid CIPP Liner in the amount of $45,000 resulting in no change to contingency. Overall contract increases from $250,022 to $295,022
Attachments: 1. Unit O-19 Change Order No.1.pdf

Title

Contract Amendment and Change Order No. 1 to contract 81-19 for Unit O-19 CIPP Liner for slip lining of deteriorated 36" Storm Sewer in lieu of originally bid CIPP Liner in the amount of $45,000 resulting in no change to contingency.  Overall contract increases from $250,022 to $295,022