Title:
|
Approve Change Order No. 1 to contract 47-16 for Unit H-15 Sewer and Forcemain, Spartan Drive and Haymeadow Avenue for adjustments to final installed quantities for seed and mulch, extra stone and backfill materials for wet well construction in the amount of $11,459.75, resulting in a decrease to the contingency from $20,000 to $8,540.25. No change to overall contract amount.
|