Title:
|
Contract 22-25 was awarded to Al Dix Construction, Inc. for $1,008,850 with no contingency for Unit DE-25 Miscellaneous Sidewalk and Concrete Street Excavation Repairs. There were no change orders. Final contract amount is $997,970.86 with no contingency. Payments issued to date total $672,778.75. Request final payment of $325,192.11.
|