Title: Request to reject awarding Wastewater Treatment Plant S-Building Air Handler Replacement to B&P Mechanical for a contract amount of $168,000 and approve the following budget adjustment: Wastewater Capital Projects S-Building Air Handler Replacement Project - $112,190 Elec Transformer and Switchgear Replacement Proj +$112,190 to re-allocate funds to another project.
Attachments: 1. 2015 Wastewater Plant Bid Recommendation to Deny.pdf

Title

Request to reject awarding Wastewater Treatment Plant S-Building Air Handler Replacement to B&P Mechanical for a contract amount of $168,000 and approve the following budget adjustment:

 

Wastewater Capital Projects

S-Building Air Handler Replacement Project                                                                           - $112,190

Elec Transformer and Switchgear Replacement Proj                                          +$112,190

 

to re-allocate funds to another project.