Title: Contract 3-26 was awarded to Kruczek Construction Inc. for $357,000 with a contingency of $35,000 for U-26 Water Reconstruction, S/o I-41. Change orders were approved totaling $13,510.50. Final contract amount is $370,510.50 with a contingency of $21,489.50. Payments issued to date total $341,462.30. Request final payment of $29,048.20.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Contract 3-26 was awarded to Kruczek Construction Inc. for $357,000 with a contingency of $35,000 for U-26 Water Reconstruction, S/o I-41. Change orders were approved totaling $13,510.50. Final contract amount is $370,510.50 with a contingency of $21,489.50. Payments issued to date total $341,462.30. Request final payment of $29,048.20.