Title:
|
Contract 56-17 was awarded to Cardinal Construction Co., Inc for the 2017 Wastewater Asbestos Removal and Remodeling project in the amount of $111,415 with a contingency of 10%. Change orders issued to date total $5,937. Payments issued to date total $92,854. Request to issue the final contract payment of $24,497.78.
|