File #: 13-1524    Version: 1 Name:
Type: Presentation Status: Filed
File created: 10/16/2013 In control: Finance Committee
On agenda: 10/23/2013 Final action: 10/23/2013
Title: Contract 11-13 was awarded to Fischer-Ulman Construction, Inc. for $210,000.00 without a contingency for sidewalk reconstruction. No change orders were approved. Final contract amount is $210,000.00 without a contingency. Payment issued to date totals $170,571.01. Request to issue the final contract payment of $35,254.44.
Title
Contract 11-13 was awarded to Fischer-Ulman Construction, Inc. for $210,000.00 without a contingency for sidewalk reconstruction.  No change orders were approved. Final contract amount is $210,000.00 without a contingency.  Payment issued to date totals $170,571.01.  Request to issue the final contract payment of $35,254.44.