Title: Change Order #5 to Staab Construction contract as part of the 2019 AWWTP Improvements Projects totaling $15,110 resulting in a decrease in contingency from $251,110 to $236,000
Attachments: 1. 220114_Finance Memo 2019 AWWTP Improvements Staab Change Order No5.pdf, 2. 2019 AWWTP Improvements Staab Change Order No5.pdf

Title

Change Order #5 to Staab Construction contract as part of the 2019 AWWTP Improvements Projects totaling $15,110 resulting in a decrease in contingency from $251,110 to $236,000