Contract 18-13 was awarded to Fischer Ulman Construction, Inc. for $250,400.00 without a contingency for miscellaneous concrete and street excavation repairs. No change orders were approved. Final contract amount is $250,400.00 without a contingency. Previous payments total $80,223.11. Request final payment of $108,256.16.