Title
Approve Contract Amendment/Change Order No. 1 to Contract 5-15 for Unit W-15 Sewer & Water Reconstruction No. 1 with Van Straten Construction Co., Inc. to increase for upsizing of stormwater infrastructure per West Wisconsin Avenue Flood Study recommendations and additional quantities of water main, valves and services in the amount of $60,420.00 resulting in a decrease to contingency from $100,000.00 to $87,080.00. Overall contract increased from $2,596,405.00 to $2,643,905.00.