Title: Change Order No 6 to Staab Construction contract as part of the 2019 AWWTP Improvements Projects totaling $19,155 resulting in a decrease in contingency from $236,000 to $216,845
Attachments: 1. 2019 AWWTP Improvements Staab Change Order No6.pdf, 2. 2019 AWWTP Improvements Project_CO6_Fully Executed.pdf

Title

Change Order No 6 to Staab Construction contract as part of the 2019 AWWTP Improvements Projects totaling $19,155 resulting in a decrease in contingency from $236,000 to $216,845