File #: 22-1071    Version: 1 Name:
Type: Presentation Status: Filed
File created: 8/17/2022 In control: Finance Committee
On agenda: 8/22/2022 Final action: 8/22/2022
Title: Contract 59-21 was awarded to Cardinal Construction Co for the 2021 AWWTP Lower Substation Building Renovation Project in the amount of $303,395 with a contingency of $36,407. Two change orders were issued that total $30,724 to lower the top elevation of the mixed liquor channel and installing new building windows. Payments to date total $317,413.42. Request to issue the final contact payment of $16,705.98

Title

Contract 59-21 was awarded to Cardinal Construction Co for the 2021 AWWTP Lower Substation Building Renovation Project in the amount of $303,395 with a contingency of $36,407. Two change orders were issued that total $30,724 to lower the top elevation of the mixed liquor channel and installing new building windows. Payments to date total $317,413.42. Request to issue the final contact payment of $16,705.98