Title: Change Orders #1 through #4 to August Winter & Sons, Inc. contract as part of the Appleton Wastewater Treatment Plant 2025 L-Building HVAC and Receiving Station Upgrades Project totaling $90,253 resulting in a decrease in contingency from $476,337 to $386,084.

Title

Change Orders #1 through #4 to August Winter & Sons, Inc. contract as part of the Appleton Wastewater Treatment Plant 2025 L-Building HVAC and Receiving Station Upgrades Project totaling $90,253 resulting in a decrease in contingency from $476,337 to $386,084.