File #: 25-0644    Version: 1 Name:
Type: Report Action Item Status: Action Item
File created: 6/4/2025 In control: Finance Committee
On agenda: 6/9/2025 Final action:
Title: Approve Change Order #6 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $111,247 resulting in a decrease in contingency from $134,357 to $23,110
Attachments: 1. 250603_Finance Info Memo AWWTP HEX ReplacementChangeOrderNo6-rev.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TItle

Approve Change Order #6 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $111,247 resulting in a decrease in contingency from $134,357 to $23,110