File #: 21-0883    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 6/16/2021 In control: Finance Committee
On agenda: 6/21/2021 Final action: 6/21/2021
Title: Contract 133-20 was awarded to Cardinal Construction Co. for the 2020 Wastewater Asbestos Flooring Removal project in the amount of $38,797 with a contingency of $3,880. One change order was issued in the amount of $1,513 to make additional asbestos removals. No payments have been made to date. Request to issue the final contract payment of $40,310.60

Title

Contract 133-20 was awarded to Cardinal Construction Co. for the 2020 Wastewater Asbestos Flooring Removal project in the amount of $38,797 with a contingency of $3,880. One change order was issued in the amount of $1,513 to make additional asbestos removals. No payments have been made to date. Request to issue the final contract payment of $40,310.60