Title: Change Orders #9 through #12 to Staab Construction contract as part of the AWWTP Phase 2 Belt Filter Press Equipment Upgrades Project totaling $147,164 resulting in a decrease in contingency from $530,312 to $383,130.

Title

Change Orders #9 through #12 to Staab Construction contract as part of the AWWTP Phase 2 Belt Filter Press Equipment Upgrades Project totaling $147,164 resulting in a decrease in contingency from $530,312 to $383,130.