Title
Approve Contract Amendment/Change Order No. 2 to Contract 1-13 for AEHS Stormwater Storage Project Unit T-11 with Radtke Contractors, Inc. to Increase for Quantities Associated with Phase 2 Plan Changes from GRAEF and StormTrap in the Amount of $125,000 and an Increase to Contingency from $60,750.13 to $200,750.13. Overall Contract Amount Increases from $3,448,485 to $3,713,485.