Title:
|
Contract 36-22 was awarded to Van Ert Electric Co. for $1,595,000 with a contingency of $159,500 for the Substation Upgrade - Phase 5. Change orders were approved totaling $35,988.04. Final contract amount is $1,630,988.04 with a contingency of $123,511.96. Payments issued to date total $1,549,438.64. Request final payment of $81,549.40.
|