Request to approve Change Order No. 2 to contract 21-24 for H-23 Lightning Drive Extension Phase 1 for added drain tile and earthwork, in the amount of $72,830.00 resulting in a decrease in contingency from $92,934.82 to $20,104.82. Overall contract increases from $1,622,361.12 to $1,695,191.12.
|