File #: 24-0959    Version: 1 Name:
Type: Report Action Item Status: Action Item
File created: 7/18/2024 In control: Finance Committee
On agenda: 7/22/2024 Final action:
Title: Request to approve Change Order No. 2 to contract 21-24 for H-23 Lightning Drive Extension Phase 1 for added drain tile and earthwork, in the amount of $72,830.00 resulting in a decrease in contingency from $92,934.82 to $20,104.82. Overall contract increases from $1,622,361.12 to $1,695,191.12.
Attachments: 1. H-23 Change Order 2 Finance Memo Final.pdf, 2. Copy of H-23 Change Order 2 Final.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Request to approve Change Order No. 2 to contract 21-24 for H-23 Lightning Drive Extension Phase 1 for added drain tile and earthwork, in the amount of $72,830.00 resulting in a decrease in contingency from $92,934.82 to $20,104.82. Overall contract increases from $1,622,361.12 to $1,695,191.12.