Title
Change Order No. 1 to Contract 6-14 for Unit W-14 Sewer & Water Main Reconstruction No. 1 with Kruczek Construction, Inc. to increase for the addition of one storm manhole on Eldorado Street and one storm inlet on Green Bay Road in the amount of $4,800.00 resulting in a decrease to contingency from $75,000.00 to $70,200.00. No change to overall contract amount.