File #: 14-1697    Version: 1 Name:
Type: Presentation Status: Filed
File created: 10/1/2014 In control: Finance Committee
On agenda: 10/8/2014 Final action: 10/8/2014
Title: Change Order No. 1 to Contract 6-14 for Unit W-14 Sewer & Water Main Reconstruction No. 1 with Kruczek Construction, Inc. to increase for the addition of one storm manhole on Eldorado Street and one storm inlet on Green Bay Road in the amount of $4,800.00 resulting in a decrease to contingency from $75,000.00 to $70,200.00. No change to overall contract amount.
Attachments: 1. Unit W-14 Change Order No 1.pdf
Title
Change Order No. 1 to Contract 6-14 for Unit W-14 Sewer & Water Main Reconstruction No. 1 with Kruczek Construction, Inc. to increase for the addition of one storm manhole on Eldorado Street and one storm inlet on Green Bay Road in the amount of $4,800.00 resulting in a decrease to contingency from  $75,000.00 to $70,200.00.  No change to overall contract amount.