Title:
|
Contract 1-13 was awarded to Radtke Contractors, Inc. for $2,242,378.07 with a contingency of $200,750.13 for Appleton East Stormwater Storage Phase 2. Change orders were approved totaling -$20,000. Final contract amount is $2,222,378.07 with a contingency of $220,750.13. Payments issued to date total $2,085,407.44. Request final payment of $51,279.01.
|