File #: 14-1894    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 11/5/2014 In control: Utilities Committee
On agenda: 11/11/2014 Final action: 12/9/2014
Title: Change Order #1 for Wastewater Fire Protection System, Phase III, to increase for additional fire alarm cable in the amount of $3,106 resulting in a decrease to the contingency from $10,000 to $6,894. No change to overall contract amount.
Attachments: 1. 2014 WW-Fire Protection Phase III CO1.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Change Order #1 for Wastewater Fire Protection System, Phase III, to increase for additional fire alarm cable in the amount of $3,106 resulting in a decrease to the contingency from $10,000 to $6,894. No change to overall contract amount.