Title:
|
Request to approve contract amendment and Change Order No 1 to contract 18/16 for Unit W-16 Sewer and Water Reconstruction No. 1 for an additional 60 LF of steel casing pipe installation due to an unforeseen underground obstruction encountered during pipe boring in the amount of $36,204 resulting in a decrease to the contingency from $93,135 to $73,428. Overall contract increased from $2,640,946 to $2,657,443.
|