File #: 19-1349    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 9/5/2019 In control: Finance Committee
On agenda: 9/9/2019 Final action: 9/9/2019
Title: Change Order No. 1 to contract 2-19 for Unit I-18 Oneida Street Bridge over Jones Park for a reduction in project contingency to offset additional construction managements costs (separate contract) in the amount of $25,000 resulting in a decrease to contingency from $124,856 to $99,856. Overall contract decreases from $5,585,697 to $5,560,697
Attachments: 1. Unit I-18 Change Order No.1.pdf

Title

Change Order No. 1 to contract 2-19 for Unit I-18 Oneida Street Bridge over Jones Park for a reduction in project contingency to offset additional construction managements costs (separate contract) in the amount of $25,000 resulting in a decrease to contingency from $124,856 to $99,856.  Overall contract decreases from $5,585,697 to $5,560,697