Title:
|
Contract 108-22 was awarded to Milbach Construction Services Co for $72,000 with a contingency of $7,200 for Water Lake Station Gate Improvements. Change orders were approved totaling $2,580. Final contract amount is $74,580 with a contingency of $4,620. Payments issued to date total $63,742.77. Request final payment of $10,837.03
|