File #: 23-1006    Version: 1 Name:
Type: Presentation Status: Filed
File created: 8/16/2023 In control: Finance Committee
On agenda: 8/21/2023 Final action: 8/21/2023
Title: Contract 108-22 was awarded to Milbach Construction Services Co for $72,000 with a contingency of $7,200 for Water Lake Station Gate Improvements. Change orders were approved totaling $2,580. Final contract amount is $74,580 with a contingency of $4,620. Payments issued to date total $63,742.77. Request final payment of $10,837.03

Title

Contract 108-22 was awarded to Milbach Construction Services Co for $72,000 with a contingency of $7,200 for Water Lake Station Gate Improvements. Change orders were approved totaling $2,580.  Final contract amount is $74,580 with a contingency of $4,620.  Payments issued to date total $63,742.77.  Request final payment of $10,837.03