Title
Change Order No. 2 to Contract 22-13 for Unit U-13 Cherryvale Avenue Sanitary, Storm, Water Main, Grading & Graveling with Carl Bowers & Sons Construction Co., Inc.to increase for undercutting and installation of extra stone base prior to asphalt paving in areas of poor subgrade in the amount of $7,950.67 resulting in a decrease to contingency from $35,000.00 to $27,049.33. No change to overall contract amount.