Title: Contract 65-16 was awarded to MCC, Inc for the 2016 Wastewater Hardscapes repairs project in the amount of $118,031 with a contingency of $17,000. One change order was issued. Payments issued to date total $109,897.94. Request final payment of $5,784.
Attachments: 1. 2016 Wastewater Hardscape Repairs Final Payment.pdf

Title

Contract 65-16 was awarded to MCC, Inc  for the 2016 Wastewater Hardscapes repairs project in the amount of $118,031 with a contingency of $17,000.  One change order was issued.  Payments issued to date total $109,897.94.  Request final payment of $5,784.