Title:
|
Change Order No. 1 to contract 76-21, Unit L-21 Sewer and Water Construction - Lightning and Edgewood, to add mechanically restrained joints and water connection/meter assembly for stream crossing per new DNR standards in the amount of $5,525.00. This change order reduces contingency from $50,000.00 to $44,475.00. Overall contract amount remains unchanged.
|