File #: 21-1703    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 12/2/2021 In control: Finance Committee
On agenda: 12/6/2021 Final action: 12/15/2021
Title: Change Order No. 1 to contract 76-21, Unit L-21 Sewer and Water Construction - Lightning and Edgewood, to add mechanically restrained joints and water connection/meter assembly for stream crossing per new DNR standards in the amount of $5,525.00. This change order reduces contingency from $50,000.00 to $44,475.00. Overall contract amount remains unchanged.
Attachments: 1. Finance Committee - Unit L-21 Change Order No. 1.pdf

Title

Change Order No. 1 to contract 76-21, Unit L-21 Sewer and Water Construction - Lightning and Edgewood, to add mechanically restrained joints and water connection/meter assembly for stream crossing per new DNR standards in the amount of $5,525.00.  This change order reduces contingency from $50,000.00 to $44,475.00.  Overall contract amount remains unchanged.