Title
Contract 13-13 was awarded to Murphy Concrete and Construction Inc. "Summit Park Tennis Court Project" for
$88,646.52 with a contingency of $4,400. One change order was issued for ($2,325). The final contract amount
$86,321.52 with a remaining contingency of $4,400. Payments issued to date total $52,186.44. Request to issue the
final contract payment of $34,135.08.