File #: 24-1627    Version: 1 Name:
Type: Presentation Status: Filed
File created: 1/2/2025 In control: Finance Committee
On agenda: 1/6/2025 Final action: 1/6/2025
Title: Contract 84-22 was awarded to Miron Construction for $5,330,989 with a contingency of $799,648 for Sludge Storage Addition. Change orders were approved totaling $280,400.48. Final contract amount is $5,611,389.48 with a contingency of $519,247.52. Payments issued to date total $5,601,389.48. Request final payment of $10,000.

Title

Contract 84-22 was awarded to Miron Construction for $5,330,989 with a contingency of $799,648 for Sludge Storage Addition. Change orders were approved totaling $280,400.48. Final contract amount is $5,611,389.48 with a contingency of $519,247.52.  Payments issued to date total $5,601,389.48. Request final payment of $10,000.