Title
Change Order No. 1 to Contract 1-15 for Unit S-15 Birchwood Stormwater Pond with Peters Concrete Co. to increase for additional quantities of drain tile installation and sidewalk replacement in the amount of $7,446.25 resulting in a decrease to contingency from $23,000.00 to $15,553.75. No change to overall contract amount.