Title: Request to approve change order #13 to Staab Construction contract as part of the AWWTP Phase 2 Belt Filter Press Equipment Upgrades Project totaling $31,042 resulting in a decrease in contingency from $383,130 to $352,088.
Attachments: 1. 260604_Finance Memo_Phase 2 BFP Change Orders13_Staab.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Request to approve change order #13 to Staab Construction contract as part of the AWWTP Phase 2 Belt Filter Press Equipment Upgrades Project totaling $31,042 resulting in a decrease in contingency from $383,130 to $352,088.