File #: 25-1135    Version: 1 Name:
Type: Report Action Item Status: Action Item
File created: 9/18/2025 In control: Finance Committee
On agenda: 9/22/2025 Final action: 9/22/2025
Title: Contract 159-23 was awarded to August Winter & Sons for $573,355 with a contingency of $57,336 for Grit System & Raw Sludge Pump Replacement. Change orders were approved totaling $35,009. Final contract amount is $608,354 with a contingency of $22,327. Payments issued to date total $592,954.67. Request final payment of $15,399.33.

Title

Contract 159-23 was awarded to August Winter & Sons for $573,355 with a contingency of $57,336 for Grit System & Raw Sludge Pump Replacement. Change orders were approved totaling $35,009. Final contract amount is $608,354 with a contingency of $22,327. Payments issued to date total $592,954.67. Request final payment of $15,399.33.