Title: Contract 161-25 was awarded to Advance Construction, Inc. for $119,802.75 with a contingency of $11,980.27 for G-26 Stormwater Pond Dredging. Change orders were approved totaling $11,963.59. Final contract amount is $131,766.34 with a contingency of $0. Payments issued to date total $125,178.02 Request final payment of $6,588.32.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Contract 161-25 was awarded to Advance Construction, Inc. for $119,802.75 with a contingency of $11,980.27 for G-26 Stormwater Pond Dredging. Change orders were approved totaling $11,963.59. Final contract amount is $131,766.34 with a contingency of $0. Payments issued to date total $125,178.02 Request final payment of $6,588.32.