File #: 23-1347    Version: 1 Name:
Type: Presentation Status: Filed
File created: 11/2/2023 In control: Finance Committee
On agenda: 11/6/2023 Final action: 11/6/2023
Title: Contract 120-22 was awarded to RJM Construction, LLC. for the 2022 AWWTP F1 Building Renovation Project in the amount of $271,840 with a 15% contingency of $40,776. Three change orders were issued in the amount of $12,505. Payments to date total $264,974. Request to issue the final contract payment of $19,371.

Title

Contract 120-22 was awarded to RJM Construction, LLC. for the 2022 AWWTP F1 Building Renovation Project in the amount of $271,840 with a 15% contingency of $40,776. Three change orders were issued in the amount of $12,505. Payments to date total $264,974. Request to issue the final contract payment of $19,371.