Title:
|
Request to approve Contract Amendment and Change Order No. 1 to contract 21-24 for H-23 Lightning Drive Extension Phase 1 for excavation below subgrade and extra stone base, in the amount of $77,508.00 resulting in a decrease in contingency from $116,000.00 to $92,934.82. Overall contract increases from $1,544,853.12 to $1,622,361.12.
|