File #: 24-0667    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 5/16/2024 In control: Finance Committee
On agenda: 5/20/2024 Final action: 6/5/2024
Title: Request to approve Contract Amendment and Change Order No. 1 to contract 21-24 for H-23 Lightning Drive Extension Phase 1 for excavation below subgrade and extra stone base, in the amount of $77,508.00 resulting in a decrease in contingency from $116,000.00 to $92,934.82. Overall contract increases from $1,544,853.12 to $1,622,361.12.
Attachments: 1. H-23 Change Order 1 Contract Amend Memo.pdf, 2. H-23 Change Order 1.pdf

Title

Request to approve Contract Amendment and Change Order No. 1 to contract 21-24 for H-23 Lightning Drive Extension Phase 1 for excavation below subgrade and extra stone base, in the amount of $77,508.00 resulting in a decrease in contingency from $116,000.00 to $92,934.82. Overall contract increases from $1,544,853.12 to $1,622,361.12.