File #: 23-0564    Version: 1 Name:
Type: Report Action Item Status: Action Item
File created: 5/18/2023 In control: Finance Committee
On agenda: 5/22/2023 Final action: 5/22/2023
Title: Change Orders #1 and #2 Miron Construction contract as part of the 2019 AWWTP Improvement Projects totaling $58,406.96, resulting in a decrease in contingency from $799,648 to $741,241.
Attachments: 1. 230509_Finance Memo SSB Addtion Miron Change Orders No1 and 2 (002).pdf

Title

Change Orders #1 and #2 Miron Construction contract as part of the 2019 AWWTP Improvement Projects totaling $58,406.96, resulting in a decrease in contingency from $799,648 to $741,241.