File #: 14-43    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 1/2/2014 In control: Utilities Committee
On agenda: 1/7/2014 Final action: 1/7/2014
Title: Approval of Contract to Staab Construction Corporation for Regulatory Upgrades and Process Improvements to the Appleton Water Treatment Facility in the amount of $4,857,000 with a 15% contingency of $728,550 and a project total not to exceed $5,585,550. Approve Budget adjustment of $361,923; $250,000 from positive budget variance from Water Distribution Capital Improvements and $111,923 from fund balance. This item will also be an Action Item at the Finance Committee.
Attachments: 1. RUPIP Construction Contract Award - STAAB Construction.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Approval of Contract to Staab Construction Corporation for Regulatory Upgrades and Process Improvements to the Appleton Water Treatment Facility in the amount of $4,857,000 with a 15% contingency of $728,550 and a project total not to exceed $5,585,550.
 
Approve Budget adjustment of $361,923; $250,000 from positive budget variance from Water Distribution Capital Improvements and $111,923 from fund balance.
 
This item will also be an Action Item at the Finance Committee.