File #: 14-279    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 2/13/2014 In control: Committee of the Whole
On agenda: 2/19/2014 Final action: 2/19/2014
Title: Approve Contract Amendment/Change Order No. 1 to Contract 1-13A for AEHS Stormwater Storage Project Unit T-11 - Precast Concrete Units with StormTrap to Increase for Redesigned Phase 2 Units and Additional Shipping Costs in the Amount of $45,000 and an Increase to Contingency from $15,000 to $25,000. Overall Contract Amount Increases from $3,544,134 to $3,599,134.
Title
Approve Contract Amendment/Change Order No. 1 to Contract 1-13A for AEHS Stormwater Storage Project Unit T-11 - Precast Concrete Units with StormTrap to Increase for Redesigned Phase 2 Units and Additional Shipping Costs in the Amount of $45,000 and an Increase to Contingency from $15,000 to $25,000.  Overall Contract Amount Increases from $3,544,134 to $3,599,134.