Title: Contract 120-22 was awarded to RJM Construction for $271,840 with a contingency of $40,776 for F-1 Bldg Improvements FMD. Change orders were approved totaling $12,505. Final contract amount is $284,345 with a contingency of $28,271. Payments issued to date total $264,974. Request final payment of $19,371.00

Title

Contract 120-22 was awarded to RJM Construction for $271,840 with a contingency of $40,776 for F-1 Bldg Improvements FMD. Change orders were approved totaling $12,505.  Final contract amount is $284,345 with a contingency of $28,271.  Payments issued to date total $264,974.  Request final payment of $19,371.00